Over-budget West 91大黄鸭 City Hall needs $200K in improvements

The building, originally budgeted at $18 million, came in significantly over budget at $22.79 million
web1_231129-wek-cityhall-claim-westkhall_1
The new West 91大黄鸭 City Hall under construction in November 2023. Photo | City of West 91大黄鸭

West 91大黄鸭 City Hall, which opened in May, is set to undergo further upgrades.

The building, originally budgeted at $18 million, came in significantly over budget at $22.79 million. Construction delays stretched the timeline for months, and the city was named in a civil lawsuit related to the project in November 2023.

The city is planning to spend $115,000 on acoustic improvements for council chambers and $85,000 to design parking lot upgrades and expansion. This week, staff will ask council for . Both projects will be funded through the city鈥檚 capital reserves. In addition to these upgrades, another $227,920 has been requested to replace council chambers' equipment under the Information Services budget.

Other requests include:

  • $700,000 to replace the roofs on Fire Halls #33 and #34;
  • $18,000 to replace a furnace and $290,000 for locker upgrades at Johnson Bentley Memorial Aquatic Centre;
  • $700,000 for a roof replacement and $600,000 for a condenser at Jim Lind Arena.

All funding for these projects would come from city reserves.

Council will review the , which includes a proposed 8.3 per cent property tax increase, during meetings on December 18-19.