91大黄鸭

Skip to content

Costs go up for Peachland water treatment plant project

Staff asked for more funding to get the project to the finish line
26137508_web1_Peachland-water-treatment-plant_1
Part of the Peachland water treatment plant during construction. (District of Peachland/Facebook)

Peachland鈥檚 water treatment plant project may almost be done, but it needs a bit more money to get it to the finish line.

The district鈥檚 director of operations, Shawn Grundy, said during an Aug. 10 council meeting there are some overages for the water treatment plant and the Trepanier Interconnect projects, asking council to approve the transfer of $900,000 from the water improvement plant to the capital budgets fund to finish off the two projects.

The district鈥檚 water treatment plant started providing service earlier in the year, which meant less boil water advisories for the majority of Peachland,鈥 Grundy said.

鈥淭he Interconnect project does continue as noted and anticipated to be substantially complete in late September.鈥

鈥淥nce complete, all the serviced areas of the district will be supplied with filtered water from Peachland Creek.鈥

But as both projects draw to a close, he added that the department has identified the need for extra funding.

鈥淏ut one of the most important things to know is that both of these projects were entered into lean. Projects of this scope typically have anywhere from 10 to 12 per cent in contingency. The water treatment plant started with four per cent and the Interconnect with seven, so we were low on both,鈥 he said.

Grundy also reassured council that the additional funds won鈥檛 affect water rates for district customers.

READ MORE:

Jeremy Clowes with Urban Systems, the contractor the district is working with for the projects. He outlined part of the reason the costs are going up was because of several challenges with electrical service to the plant, natural gas service and equipment.

Now with a proposed backwash recycling treatment to add to the plant, there is more to think about.

Since starting operation three months ago, Clowes said they found other areas in the plant where operation could be improved, hence the request for additional funding.

Regarding the Trepanier Interconnect, the line that will service the rest of the district, the project is nearly finished, with the pipeline now being pressure-tested. Clowes acknowledged completing the Interconnect has taken much longer than anticipated.

鈥淭he project was originally to be completed at the end of April and had included a three-month winter break,鈥 he said.

鈥(The line) is expected to reach substantial performance in late September.鈥

This means an additional eight months of construction time on the project, adding up costs. Part of the overage stems from COVID-19-induced delays with valve parts.

Grundy said the new amount they鈥檙e asking for already has contingencies built into it.

鈥淲e鈥檙e hoping to ask more than what we need so that we don鈥檛 have to come back to you again because we鈥檝e (already) come back a few times,鈥 he said.

鈥淚f we had a higher contingency level (for the projects), yes, we would鈥檝e been within budget.鈥

Council approved the extra funding.

READ MORE:



twila.amato@blackpress.ca

Like us on and follow us on .



Twila Amato

About the Author: Twila Amato

Twila was a radio reporter based in northern Vancouver Island. She won the Jack Webster Student Journalism Award while at BCIT and received a degree in ancient and modern Greek history from McGill University.
Read more



(or

91大黄鸭

) document.head.appendChild(flippScript); window.flippxp = window.flippxp || {run: []}; window.flippxp.run.push(function() { window.flippxp.registerSlot("#flipp-ux-slot-ssdaw212", "Black Press Media Standard", 1281409, [312035]); }); }